Calendar Setup: Amend the public holiday to a working day in the calendar setup

How to change a full day to a half day? Remove the PH in the calendar.

Updated this week

You can follow the steps below to change manually on each day in the calendar:

  1. Go to the Core module, click Calendar Setup.

  2. Select the Calendar ID.

  3. Click Work Calendar or Leave Calendar.

  4. Click on the day you would like to change.

  5. Right-click and change to F (full day), H (half day), or O (off day) as required.